One of the fundamental questions for any schedule health assessment is “Is the schedule logically driven?” There are some scheduling metrics that could help planners and schedulers to find the answer to this question. In this post, we will review some of them, that are related to missing dependencies.
Missing Dependencies Metrics
Missing logic metrics is a group of metrics known as:
- missing dependencies,
- missing predecessors and successors,
- open start & finish,
- dangling activities.
This check is not as simple as many project managers and schedulers might think. In fact, it is actually very hard to answer the question: Are there any missing or incorrect dependencies in the schedule?
A very popular DCMA-14 Points schedule assessment includes a check of logic (metric N1). Schedulers who are familiar with a scheduling tool (usually Primavera or Microsoft Project) but lacking scheduling knowledge very often apply DCMA-14 “blindly”. Their schedule may have critical logical issues but is reported as a schedule with sufficient quality. I have seen this issue in small business projects and also in large construction programs. So, let’s review what needs to be considered for a comprehensive schedule logic analysis.
Missing Dependencies?
There is no metric that could confirm that a schedule has no dependencies missing.
The fact that each activity (except first and last) has a predecessor and successor doesn’t mean that another successor from/to this activity is not missing. The only way to guarantee that a schedule has correct logic is to implement correct schedule development and maintenance processes and apply control to ensure these processes are followed.
Each reporting period logic changes have to be analysed, documented and explained.
While scheduling metrics can’t guarantee that dependencies are not missing, some of them are good indicators that logic has to be checked and, if required, fixed. There are four primary schedule quality metrics used to indicate that a schedule may have a missing dependency:
♣ Missing Predecessor

All ‘Not Completed’ activities except 1st activity and external incoming activities must have a predecessor(s).
♣ Missing Successor

All ‘In Progress’ or ‘Not Started’ activities except the last activity and external outcoming activities must-have a successor(s).
♣ Open Start

Activities where only the predecessor(s) are either ‘Finish-to-Finish’ or Start-to-Finish resulting in an open start to the activity. All ‘Not Completed’ activities except 1st activity and external incoming activities must have at least one ‘Finish-to Start’ or ‘Start-to-Start’ predecessor.
♣ Open Finish

Activities where the only successor(s) are either ‘Start-to-Finish’ or ‘Start-to-Start’ resulting in an open finish to the activity. All ‘In Progress’ or ‘Not Started’ activities except the last activity and external outcoming activities must have at least one ‘Finish-to-Start’ or ‘Finish-to-Finish’ successor.
There is a number of points that have to be taken into consideration when these metrics are applied:
- A project may have external dependencies and it is not always possible, and in some cases, not recommended to link schedules from different projects. Milestones representing such dependencies do not have predecessors or successors.
- A Project may have Level of Effort (LoE), Hammock and WBS activities. Different scheduling tools implement these types of activities differently and this impacts the “missing logic” analysis.
– Hummocks in MS Project are shown without a predecessor and a successor but there is no way to identify “Hammock” type of activities in the system.
– “WBS summary” activities in Primavera don’t need a predecessor or a successor. So they have to be excluded from the analysis. Another metric is required to check that “WBS summary” activities don’t have logic as Primavera permits linking activity to “WBS summary” activity.
– In Primavera, if all activity successors are linked to LoE or “WBS summary” activities, the activity is actually missing a valid successor. Otherwise, based on the logic, there are no requirements to complete this activity. The same is applicable to predecessors. Such cases could only be identified via a specially developed project report, not via filters.
- If a milestone has “Open Start” or “Open Finish” it actually doesn’t create any issues with logic. Milestones could be excluded from these metrics.
- Microsoft Project has a unique feature to link activities with summary tasks. If this technique is applied it is very hard to analyse logic, as some of the activities are driven by logic from activities and some from summary tasks, so it is not recommended. An additional metric is required to identify summary tasks with processors and successors.
Filters
Missing logic metrics could be developed via filters in Primavera and Microsoft Project but, as described above, specifics of each tool have to be taken into account. Spider Project already has all these metrics build-in and also allows developing comprehensive additional filters as required.
Primavera filters to identify activities with missing logic:
♣ No Predecessors

♣ No Successors

♣ Open Finish

♣ Open Start

External Schedule Analysis Tools
When an external schedule analysis tool is used each metric has to be configured to address explained challenges. For example, Acumen Fuse has a pre-developed “Missing predecessors” metric. However, the metric includes ALL activities with missing predecessors. If an activity already started (or completed) it doesn’t matter if it has a predecessor or not. It is recommended to configure this metric to exclude these activities. Otherwise, the Acumen Fuse Report creates “noise” and may incorrectly show that the schedule has predecessors issues when it actually doesn’t.