Schedule Logic Check Metrics

Schedule Logic Check Metrics

One of the fundamental questions for any schedule health assessment is “Is the schedule logically driven?” There are some scheduling metrics that could help planners and schedulers to find the answer to this question. In this post, we will review some of them, that are related to missing dependencies.  

Missing Dependencies Metrics

Missing logic metrics is a group of metrics known as:

 

  • missing dependencies,
  • missing predecessors and successors,
  • open start & finish,
  • dangling activities.

This check is not as simple as many project managers and schedulers might think. In fact, it is actually very hard to answer the question: Are there any missing or incorrect dependencies in the schedule?

A very popular DCMA-14 Points schedule assessment includes a check of logic (metric N1). Schedulers who are familiar with a scheduling tool (usually Primavera or Microsoft Project) but lacking scheduling knowledge very often apply DCMA-14 “blindly”. Their schedule may have critical logical issues but is reported as a schedule with sufficient quality. I have seen this issue in small business projects and also in large construction programs. So, let’s review what needs to be considered for a comprehensive schedule logic analysis.

Missing Dependencies?

There is no metric that could confirm that a schedule has no dependencies missing.

The fact that each activity (except first and last) has a predecessor and successor doesn’t mean that another successor from/to this activity is not missing. The only way to guarantee that a schedule has correct logic is to implement correct schedule development and maintenance processes and apply control to ensure these processes are followed.

Each reporting period logic changes have to be analysed, documented and explained.

While scheduling metrics can’t guarantee that dependencies are not missing, some of them are good indicators that logic has to be checked and, if required, fixed. There are four primary schedule quality metrics used to indicate that a schedule may have a missing dependency:

♣   Missing Predecessor

All ‘Not Completed’ activities except 1st activity and external incoming activities must have a predecessor(s).

♣   Missing Successor

All ‘In Progress’ or ‘Not Started’ activities except the last activity and external outcoming activities must-have a successor(s).

♣   Open Start

Activities where only the predecessor(s) are either ‘Finish-to-Finish’ or Start-to-Finish resulting in an open start to the activity. All ‘Not Completed’ activities except 1st activity and external incoming activities must have at least one ‘Finish-to Start’ or ‘Start-to-Start’ predecessor.

♣   Open Finish

Activities where the only successor(s) are either ‘Start-to-Finish’ or ‘Start-to-Start’ resulting in an open finish to the activity. All ‘In Progress’ or ‘Not Started’ activities except the last activity and external outcoming activities must have at least one ‘Finish-to-Start’ or ‘Finish-to-Finish’ successor.

There is a number of points that have to be taken into consideration when these metrics are applied:

  • A project may have external dependencies and it is not always possible, and in some cases, not recommended to link schedules from different projects. Milestones representing such dependencies do not have predecessors or successors.
  • A Project may have Level of Effort (LoE), Hammock and WBS activities. Different scheduling tools implement these types of activities differently and this impacts the “missing logic” analysis. 

–   Hummocks in MS Project are shown without a predecessor and a successor but there is no way to identify “Hammock” type of activities in the system.

–   “WBS summary” activities in Primavera don’t need a predecessor or a successor. So they have to be excluded from the analysis. Another metric is required to check that “WBS summary” activities don’t have logic as Primavera permits linking activity to “WBS summary” activity.

–  In Primavera, if all activity successors are linked to LoE or “WBS summary” activities, the activity is actually missing a valid successor. Otherwise, based on the logic, there are no requirements to complete this activity. The same is applicable to predecessors. Such cases could only be identified via a specially developed project report, not via filters.

  • If a milestone has “Open Start” or “Open Finish” it actually doesn’t create any issues with logic. Milestones could be excluded from these metrics.
  • Microsoft Project has a unique feature to link activities with summary tasks. If this technique is applied it is very hard to analyse logic, as some of the activities are driven by logic from activities and some from summary tasks, so it is not recommended. An additional metric is required to identify summary tasks with processors and successors.

Filters

Missing logic metrics could be developed via filters in Primavera and Microsoft Project but, as described above, specifics of each tool have to be taken into account. Spider Project already has all these metrics build-in and also allows developing comprehensive additional filters as required.

Primavera filters to identify activities with missing logic:

♣  No Predecessors

♣  No Successors

♣  Open Finish

♣  Open Start

External Schedule Analysis Tools

When an external schedule analysis tool is used each metric has to be configured to address explained challenges. For example, Acumen Fuse has a pre-developed “Missing predecessors” metric. However, the metric includes ALL activities with missing predecessors. If an activity already started (or completed) it doesn’t matter if it has a predecessor or not. It is recommended to configure this metric to exclude these activities. Otherwise, the Acumen Fuse Report creates “noise” and may incorrectly show that the schedule has predecessors issues when it actually doesn’t.

Alex Lyaschenko

PMO | Portfolio Planning & Delivery | PMP | P3O Practitioner | AgilePM Practitioner | Six Sigma

Critical Path Drag

Critical Path Drag

Majority of project managers are familiar with the critical path method (CPM) and think that they know how to apply it to manage their projects.

Many scheduling software can compute and visualise Critical Path, so it is a no-brainer to use it. Usually, a project manager accepts the calculation as the schedule. The Critical path method doesn’t take resources, material and financial supply constraints into the consideration. So, the next steps become to assign resources, baseline the schedule and start to manage project progress.

This is because the project managers have forgotten that the “M” in CPM stands for method. The reality is that the first network is only the tentative schedule, giving just the data to implement the method fully. Once the initial CPM schedule has been computed and a logic diagram produced, the project manager is in a position to use the critical path method to save time and money. If, for instance, we want to shorten the project duration, we now know where to start: the current critical path!

There are three ways of trying to shorten the project:

1. Shorten the duration of activity on the critical path by:

  • adding extra resources
  • assigning resources with better productivity
  • ask resources to work more hours
  • change delivery method (a backhoe instead of 10 labours)
  • prune scope (gold planning)

2. Start critical activities earlier by:

  • applying anti-crashing method

3. Change logic and remove activity from the critical path by:

  • applying fast-tracking method

But the question is: Where should we add/remove these resources? Where should we review the scope? What will the effect be of such actions on the schedule and cost?

For the answers, we need CPM metrics.

One of the CPM metrics that could help us find the answers to the above questions was proposed by Stephan A. Devaux and explained in his “Total Project Control” book called Critical Path Drag. In the 1st edition, published in 1999, Stephan used the term DRAG (Devaux’s Removed Activity Guide), but since the 2nd edition, it was written as “Drag”.

In his book, Stephan described the Critical Path Drag metric as:

Critical Path Drag

Critical Path Drag is the quantification of the amount of time each activity is adding to the project.

To some extent this metric could be considered as an opposite to the Total Float metric.

Total Float

Total Float is the amount of time an activity can be delayed before its path becomes the longest path.

By contrast, drag is:

  • only#1 on the critical path; and
  • the amount of time by which an activity duration can be shortened#2 before its drag is reduced to zero.

Further decrease in the duration of the activity would not reduce the duration of the project as another path became critical. In other words, it is the amount of time that could potentially be saved on the project by reducing the duration of the activity (or removing an activity completely).

#1,2 The proposed explanation covers the majority of project scenarios, but not all of them. We will review such scenarios below.

Most of the software that computes Critical Path also could calculate Total Float (TF), but just a few can calculate Critical Path Drag, so this metric is still not well known. However, this computation is very important. Without understanding activity drags, well too often, implemented project optimisation measures don’t give the expected effect.

The formula for computing drag on a simple critical path network schedule is as follows:

  • If an activity is off the critical path, its drag = 0
  • If an activity is on the critical path and has nothing else in parallel#3, its drag = its duration
  • If an activity is on the critical path and has other activities in parallel, its drag is the lowest number between:

– activity duration
– total float of the parallel activity with the least total float

A programming formula may look something like this:
= IF (Critical = “Yes”, Min (duration, min({total float of parallel activities}), 0)

#3 Parallel activities belong to a parallel stream. They are not necessarily planned to be performed at the same time as the analysed activity.

Critical Path Drag Calculation

Let’s review the following simple project:

With all “Finish-to-Start” dependencies, the duration of this project is 18 days. Drag for first and last activities is equal to the duration of activities.
The drag for the second critical activity is only 3 days. This means that if the activity will be reduced by 3 days, the project also will be reduced by 3 days. Any further optimisation would not decrease the duration of the project as this activity would not be on the new critical path anymore.

Let’s assume it is possible to add resources to the 10-days activity and complete this activity twice quicker. The new duration of this activity will be 5 days:

The project has a new Critical Path and as we expected duration decreased to 15 days.

Drag for 2nd and 3rd critical activities is 2 days each. However, it doesn’t mean that if both activities are reduced by 2 days, the project will be 4 days shorter! The drag is not cumulative.

Negative Critical Path Drag

Let’s consider a slightly more complex example: a working typical fragment “1 km of Road Construction”. There are only 20 activities in this fragment, but there are much harder to calculate critical path drag manually. Let’s use a scheduling tool, Spider Project, to calculate CP drag for each activity:

1 km of Road Construction.

There are 10 critical activities and all of them have Critical path drag <>0. In this project fragment, the first and the last critical activities have CP drag equal to the duration of the activity. In other cases, drag is less than the activity duration. Also, there are 3 critical activities where drag is less than zero. Let’s analyse how it is possible.
As it was explained in the “Project Anti-Crashing Method” post, in some cases project duration could be reduced by increasing a critical activity duration:

In this example, the CP drag of the activity “C” will be negative. If the duration of this activity is reduced to zero, the duration of the project will be increased from 42 to 50 days. So, CP drag will be minus 8 days.
At the same time, if it is possible to increase the duration of activity “C” by 14 days, the duration of the project will be decreased from 42 to 28 days (!)

Critical Path Drag on non-critical activities

It is logical to think that project duration could be reduced by optimising activities on a critical path only. However, there are project scenarios when decreasing the duration of the non-critical activity could reduce the overall duration of the project.
In the previous post, we reviewed a project fragment when activities have different calendars.

Activity “A” only could be performed on weekdays and activity “B” only could be performed on weekends.

Activity “A” has 4 days of the total float, so it is not on the critical path. However, if we reduce the duration of this activity to 5 days, the overall duration also will be reduced from 14 days to 7 days.

So, the CP drag of activity “A” will be >0. How much exactly? Well, it depends..
If it is based on the activity “A” 5-days calendar, CP drag is 5 days. If 7-days calendar, CP drag is 7 days.

Summary

  • The Critical Path method gives project teams information to optimise their project plans, not the final schedule. The method has optimisation metrics for that.
  • Activity Drag is an important Critical Path metric that allows prediction of how the applied effort would shorten project duration
  • In some cases Activity Drag could be negative
  • When different calendars are applied non-critical activities may have a positive ‘Activity Drag’. Optimisation of these activities would shorten the project duration.

We are going to review other Critical Path optimisation metrics in future posts.

Alex Lyaschenko