Beyond DCMA 14 points. Missing dependencies.

Beyond DCMA 14 points. Missing dependencies.

A project schedule can pass every DCMA assessment and still be unreliable.

It reflects a common misunderstanding in project controls: passing schedule health checks does not prove that a schedule is correct. It only demonstrates that certain quality criteria have been satisfied.

Necessary But Not Sufficient

In mathematics, there is a concept known as a ‘Necessary but not sufficient condition’.

A necessary condition is something that must be true for a desired outcome to occur. If the condition is not met, the outcome will definitely be negative. However, satisfying a necessary condition alone does not guarantee success. Other conditions may also need to be met.

This distinction applies directly to project schedule validation.

A widely accepted rule of thumb is that every activity should have at least one predecessor and successor. While there are exceptions, this is generally considered good scheduling practice.

Having predecessors and successors is a necessary condition for a quality schedule. It is not a sufficient condition. A schedule may satisfy this rule completely and still contain missing dependencies.

Schedule Compliance vs Schedule Correctness

Common Misconception

A schedule can achieve an excellent DCMA score and still have critical quality issues.

This is not a criticism of DCMA assessments. They were never intended to prove schedule validity. Their purpose is to identify basic scheduling and performance issues. Problems arise when compliance scores are mistaken for evidence that the schedule is complete, realistic, and feasible.

Missing Dependencies

Missing dependencies create unrealistic optimism. Activities appear able to start earlier than they can in reality, resulting in delivery dates that cannot be achieved. In a schedule, the absence of a single dependency can alter the resource-critical path and reduce project duration.  

Only one missing critical dependency may be enough to invalidate the entire schedule.

Technological Dependency Validation

Technological dependencies, sometimes referred to as process dependencies, should not be identified from scratch every time a schedule is developed or reviewed.

A more mature approach is to develop a library of standardised work packages known as fragnets. Each fragnet represents a proven technological process with activities, sequencing logic, required skills, productivity assumptions, and constraints already analysed and documented. The project schedule is then assembled using these validated building blocks rather than creating logic relationships from scratch for every project.

By comparing a schedule with approved fragnets, planners can more effectively identify missing or inconsistent technological dependencies. 

This approach requires mature classification structures for activities, deliverables, and WBS elements. Without standardisation, meaningful comparison becomes difficult.

.

Good Practice

Validated fragnets enable organisations to reuse proven delivery logic and reduce the risk of missing technological dependencies.

Resource Dependency Validation

Resource dependencies are fundamentally different. Unlike technological dependencies, resource dependencies are dynamic. They need to be amended due to ongoing changes and resource supply constraints.

Attempting to manually define every resource dependency is often impractical and sometimes impossible. However, ignoring resource dependencies is likely to cause a delay.

A network may be technologically correct while remaining operationally impossible because the required resources simply do not exist when needed. Traditional schedule quality checks rarely address this challenge adequately.

This is why resource-driven scheduling methods and Resource Critical Path analysis provide insights that traditional Critical Path Method schedules often miss.

Summary

Logic validation is a crucial part of schedule analysis and it is not sufficient to only check that each activity and milestone has at least of predecessor and successor. It is obvious and essential step but analysis should not stop at that step.

Alex Lyaschenko