Project myth: Resource Critical Path matters only when resources are overloaded

Why can’t a project be effectively managed using Critical Path Method (CPM) alone?
Let’s examine a common project-management myth: Resource Critical Path matters only when resources are overloaded.
A resource-loaded schedule calculated using CPM can show the demand for each resource type. If no resource appears overloaded, and assuming there are no cash-flow gaps, the schedule is often declared feasible. This creates an illusion that CPM is sufficient for managing project delivery as long as resources are adequate to support the critical path. This assumption is flawed.
For effective management, it is necessary to understand the flexibility level of activities – how changes in start and end dates impact project duration, cost and benefits. The Network Analysis metric, Total Float, provides an opportunity to understand the impact on the end date and is an important proxy for cost and benefit analysis.
The problem is that CPM-based Total Float can be misleading.
It is calculated under the implicit assumption that resources are unlimited. In reality, no project has unlimited resources; at least some resources are always constrained.
Let’s illustrate why CPM-based Total Float can be misleading with a simple scenario.

This project has adequate resources – while two resources (Alex and Julia) are limited, they are not overloaded.

Under these conditions, the duration-driven critical path coincides with the resource-driven critical path. Let’s also compare Total Float calculated in both methods:
- DCPM (Duration-Driven Critical Path, i.e. CPM)
Under DCPM, Activity D appears to have three days of Total Float. This result would only be valid if the project had additional resources, which it does not.

- RCPM (Resource-Driven Critical Path)
When the fragment is recalculated considering resource supply limitations, Activity D has zero Total Float. Any delay in this task will delay the project end date.

This demonstrates the core issue: CPM may be sufficient for developing a wishful delivery plan under the assumption of unlimited resources, but it is not sufficient for effective project delivery because it ignores existing project constraints.
The fundamental metric, Total Float, can be misleading when resource limitations are ignored.
Still, projects continue to use Total Float as the reliably base for both predictive and descriptive analysis. Planners and forensic scheduling consultants often make a convenient assumption that the project has unlimited resources, implicitly ruling out the possibility that delays may be caused by resource limitations.
As a result, resource critical path analysis is systematically ignored. Any variance is then attributed to external events, even when constrained resources are the real driver.
By treating unlimited resources as a given, Total Float loses its meaning as a measure of real schedule flexibility. What is presented as “analysis” is often nothing more than the behaviour of an oversimplified model, detached from project realities.
In practice, projects are delivered by finite people, crews, and equipment. Ignoring those limits does not make delays disappear. It simply makes them invisible in the analysis. Effective project delivery requires Resource Critical Path management.
Alex Lyaschenko
PMO | Portfolio Planning & Delivery | PMP | P3O Practitioner | AgilePM Practitioner | Six Sigma







